In 2018 the Town of Creston received funding in the amount of $2,834,150 which was made available under the Strategic Gas Tax Grant offered by the Provincial and Federal Governments. This grant allowed the Town to construct a long-term solution to address the collection of bio-solids resulting from Creston’s Waste Water Treatment Process.

Construction was started in July 2020 by Carver Construction Limited out of Kelowna. The $3.788M project was completed in April 2021, on schedule and approximately $100,000 under budget.

The Town of Creston now has a permanent Bio Solids Handling Facility that fully addresses all BC Ministry of Environment regulations.



Do you have any questions? No problem! Just reach out below and we will get back to your shortly.


In 2018 the Town of Creston received funding in the amount of $2,834,150 which was made available under the Strategic Gas Tax Grant offered by the Provincial and Federal Governments. This grant allowed the Town to construct a long-term solution to address the collection of bio-solids resulting from Creston’s Waste Water Treatment Process.

Construction was started in July 2020 by Carver Construction Limited out of Kelowna. The $3.788M project was completed in April 2021, on schedule and approximately $100,000 under budget.

The Town of Creston now has a permanent Bio Solids Handling Facility that fully addresses all BC Ministry of Environment regulations.



Do you have any questions? No problem! Just reach out below and we will get back to your shortly.

Consultation has concluded

Do you have questions regarding our Waste Water Treatment Plant or the new Biosolids Handling System? Just reach out here! 

Enter your question and our staff will reply shortly.