Project Update for week ending Sept. 3, 2021
The Creston Emergency Services Building project continues to progress on schedule as Eagle Builders finishes the walls and the roofing base materials.
The installation of concrete wall panels began on August 18th and was wrapped up earlier this week. Eagle Builders installed steel beams and roof decking in preparation for the roof to be completed in the coming weeks. Hollow core concrete panels and steel posts were installed for the second floor in the main part of the building as well as for the mezzanine in the apparatus bays. Steel stairs were installed at both ends of the building for access to to the second floor area.
This completes a major milestone of the project and provides a visual of the new Creston Emergency Services Building.
Moving forward into the next couple of weeks, roofing for the structure will be completed. Chandos, the Construction Manager for the project, will finalize the remainder of the outstanding tender work to award contracts to sub-trades that will complete the facility.
Consultation has concluded