Project Update for week of January 14, 2022
The Creston Emergency Services Building project continues to progress on schedule. Within the last few weeks, the steel stud framing was completed. The North set of stairs were poured ,and curbs and coring were completed in the Mezzanine area.
Over the next few weeks the mechanical and electrical rough-in’s in the Administration and Apparatus spaces will be ongoing and as well as the coring in the Administration area. Installation of the backing for cabinets and washroom accessories are also set to begin. Sprinkler rough-ins, the pouring of the south stairs and southside bollard installation will be completed.
Consultation has concluded