Chandos, the construction manager for the Creston Emergency Services Building, provided the Town of Creston recommendations for the first round of tender packages.
The Town of Creston were pleased to see local contractors awarded contracts through the competitive bidding process. The construction has started at the site and is expected to be completed by spring of 2022.
The following are the results of Bid Package #1
EARTHWORK SERVICES | IronTek Land Developments Creston, BC |
$576,407 |
FORMWORK | RocTec Products Ltd. Creston, BC |
$46,800 |
REINFORCING STEEL | Shaw Steel Services Wheatland County, AB |
$92,270 |
CONCRETE SUPPLY | Sullivan Stone Creston, BC |
$142,439 |
CONCRETE PUMPING | Sullivan Stone Creston, BC |
$14,054 |
CONCRETE FINISHING | 3D Concrete Finishing Creston, BC |
$35,276 |
Share Local Contractors Awarded Contracts in First Tender Package on Facebook
Share Local Contractors Awarded Contracts in First Tender Package on Twitter
Share Local Contractors Awarded Contracts in First Tender Package on Linkedin
Email Local Contractors Awarded Contracts in First Tender Package link
Consultation has concluded